The metal roof decking has been installed at Northridge, along with metal studs and sheeting on the exterior wall. Hopefully the remainder of the roofing material will be going on today, weather permitting, and the roof should be totally completed by tomorrow. The curb ducts for 7 A.C. units have also been installed on the roof.
Footings have been dug for student benches that will be placed just outside all classroom doors of the new addition at Northridge. An ADA-complient sidewalk has also been added to the parking lot addition.
At Santa Fe, curb ducts have also been installed for the AC units at Lindley Hall. Ceiling materials have been delivered and will be installed today and the spiral duct work is scheduled to be installed at the beginning of next week.
A pre-bid conference will be held on Aug. 13 for the Santa Fe and Educational Technology Center additions. Opening bids will take place at McKinley Administrative Center on Aug. 28 at 1:30 pm.
More photos can be viewed by visiting the construction updates page.